Demolition of utility lines within campus tunnels, rerouting of water distribution lines, and grouting of abandoned tunnel sections at Woodward Resource Center. Work spans approximately 24 months with construction anticipated from July 2026 through June 2028.
Type: utility water sewer · Confidence: 75%
Watch out for
Bid Number: RFB927950-01 Agency: Administrative Services, Dept
Contact: Construction Procurement The Iowa Department of Administrative Services will be receiving bids for demolition of utilities in tunnels, re-route water lines, and fill tunnels with grout at Woodward Resource Center, Woodward, Iowa 50276. The Iowa Department of Administrative Services anticipates construction to begin on July 6, 2026 and end on June 30, 2028.